SB9 Lot Split Timeline and Steps
By SB9 Partners · Published
Homeowners often hear two very different answers when they ask how long an SB9 lot split takes. One is measured in days: the city or county has a legal deadline to approve or deny a complete application. The other is measured in months: the time from first conversation to the day you are paid, after the new home is built and sold. Those clocks are not the same, and mixing them up leads to frustration. This guide separates them, then walks through the steps in the order they usually happen.
The 60-day clock is only the city's decision
Since January 1, 2025, SB 450 has required a local agency to approve or deny a complete SB9 application for a housing development or an urban lot split within 60 days of receiving it. HCD's April 2026 fact sheet also notes that the Permit Streamlining Act gives the agency 30 days to determine whether an application is complete. If the file is incomplete, the clock does not run the way applicants hope. Cities such as Palo Alto and Thousand Oaks have written the 60-day rule, and a deemed-approved backup, into their municipal codes.
That deadline is important, but it covers only the ministerial decision on a complete application. It does not include the time to hire a surveyor, prepare a parcel map, clear title or HOA questions, get a lender to release the new parcel, design the new home, obtain building permits, build it, or sell it. Those steps sit on either side of the 60-day window.
Our project timeline: about 12 months to payout
In our homeowner partnership, we plan for about 12 months from start to payout. A typical sequence looks like this: roughly the first two months go to the survey, parcel map and split approval; the next two go to design and building permits; about seven months go to construction; and the final month goes to the sale and payout. Sometimes timelines go past 12 months due to unforeseen delays with city approval and construction. Coastal permits, utility work, fire-access issues and incomplete applications are the most common reasons a project runs long.
The steps, in order
1. Eligibility review
We start by checking whether the lot can be split under state law and whether it fits our partnership criteria. That means confirming the zone, the lot size, whether the yard is generally flat and has street access, whether the home is owner-occupied, and whether any site exclusions apply. We also look at title, easements and any HOA or CC&R documents. The legal checklist is in SB9 Lot Split Requirements: Can I Split My Lot? (Eligibility Checklist). If you don't see your county in our service area, you can still submit your lot and we'll review it.
2. A written partnership agreement
If the lot looks viable, the next step is a written partnership agreement. Your payout has two parts: a fixed amount based on the size of the new lot, plus a share of the profit based on what the new home or duplex sells for. Final terms are set in that agreement, not in a blog post or a website calculator. Until the agreement is signed, nothing about the property changes.
3. Survey, proposed lot line and parcel map
A licensed land surveyor or registered civil engineer prepares the map. The proposed line has to keep your existing house entirely on one parcel, give each new parcel at least 1,200 square feet, and keep neither parcel under 40 percent of the original lot. It also has to leave a realistic way for the new parcel to reach the street, which may mean an access easement. See SB9 minimum lot size and the 40/60 rule for how those numbers work.
4. Owner-occupancy affidavit and other recorded documents
The applicant for an urban lot split must sign an affidavit stating that they intend to occupy one of the units as their principal residence for at least three years from the date the split is approved, with a narrow exception for certain community land trusts and nonprofits. Cities use their own forms. In the City of San Diego, Form DS-3062 is recorded with the County Recorder, and Form DS-3063 is also required. Some cities record a separate covenant about short-term rentals and further splits. We explain the affidavit in a dedicated guide.
5. City or county review of the complete application
Once the application is complete, staff review it ministerially against objective standards. There is no public hearing. The 60-day clock described above applies to that decision. If the agency denies the application, SB 450 requires it to give the applicant a written list of what is deficient and how it can be remedied. Local procedures still differ. Newport Beach processes urban lot splits under Municipal Code Chapter 19.90. Palo Alto requires a parcel map under Chapter 21.10. In unincorporated Rancho Santa Fe, the County of San Diego uses an SB-9 tentative parcel map, and the recorded parcel map must also be approved by the Department of Public Works.
6. Recording the map and issuing a new APN
Approval of the tentative or parcel map is not the end of the split. Conditions have to be satisfied, and the final parcel map has to be recorded. Only then does the county assessor issue a new assessor's parcel number (APN) for the second lot. In our partnership, you keep the whole lot while the split is being approved. SB9 Partners owns the new lot once the final map is approved and a new APN is issued. If a project can't be completed, nothing happens and you keep your original lot.
7. Your lender, if you have a mortgage
If the property has a loan, the deed of trust usually covers the entire original lot. Your lender typically has to agree to release the new parcel before it can be held or sold separately. That work often runs in parallel with the map, but it can become the longest item on the list if it starts late. See doing an SB9 lot split when you have a mortgage for the questions to ask your servicer, and raise them early.
8. Design and building permits for the new home
Some cities prefer, or require, the lot split and the new-home plans to move together. The City of San Diego's Information Bulletin 409 recommends applying for both at the same time, because doing them in sequence can change what you are later allowed to build. Thousand Oaks generally will not accept an urban lot split application unless a residential development application for the new parcel is submitted with it, unless a two-unit project has already been approved. Building permits are their own process, with plan check, corrections and utility approvals. The 60-day SB9 clock does not automatically cover every later building-permit cycle.
9. Construction, sale and payout
You stay in your home while the new home or duplex is built on the split-off parcel. After construction, the new home is sold, and you are paid under the partnership agreement. Questions about how the proceeds may be taxed belong with a CPA; our tax-questions guide is a starting list, not tax advice.
What most often makes a project run long
- An incomplete application. The 60-day decision period starts when the agency has a complete file, not when the first draft is dropped off.
- Coastal review. Parcels in the Coastal Zone, including parts of Newport Beach and coastal neighborhoods in San Diego County, can need a Coastal Development Permit in addition to the lot split.
- Fire access and hazard maps. Some sites are excluded from SB9 because of fire-hazard severity zones. Even where a project is eligible, a fire district may require a turnaround or a second access point. Unincorporated lots should be checked against the local agency's map; see Rancho Santa Fe.
- Utilities, easements and HOA documents. Shared driveways, sewer laterals and recorded CC&Rs are found in title, not on a zoning map, and they take time to resolve.
- Lender review. A partial release can move slowly if the request is made after the map is already in process.
What this timeline is not
It is not a guarantee that every project finishes in 12 months, and it is not a promise that every city will use the full 60 days or finish sooner. Local codes, staffing and site conditions vary. We can only plan around the rules we can verify for your address. Read the county page that matches your lot — San Diego, Orange, Los Angeles, Santa Clara, San Mateo, Santa Barbara or Ventura — and any city page we have for your community.
Next steps
If you want a timeline that is tied to your parcel, schedule a free consultation. Bring your address, your lot size if you know it, and, if you have a mortgage, the name of your loan servicer. We'll tell you which steps apply, which agency will review the map, and where the schedule is most likely to flex.
Frequently asked questions
Does the 60-day deadline cover construction and sale?
No. It covers the local agency’s decision on a complete SB9 application. Surveying, title work, lender releases, building permits, construction and sale are outside that decision window.
What are the main steps before payout?
The sequence includes eligibility review, a written agreement, survey and parcel map, the owner-occupancy affidavit, agency review, recording and a new APN, lender work where needed, design and building permits, then construction and sale.
What can make the project take longer?
Incomplete applications, coastal review, fire-access questions, utilities, easements, HOA documents and late lender review can delay the project. About 12 months is a plan, not a guaranteed completion date.
This article is general information, not legal, tax or lending advice. Rules change and vary by city; confirm details with the city, your lender, a CPA and a real estate attorney before deciding.