    SB9 Lot Splits in Thousand Oaks

    A full local SB9 article, including a rule that the new-home plans are filed with the split

    Thousand Oaks implements SB9 in Municipal Code Title 9, Chapter 4, Article 37, Urban Lot Splits and Two-Unit Housing Developments. The eligibility, application and development standards are in §§ 9-4.3704 through 9-4.3708. The article was most recently amended by Ordinance 1739-NS, effective October 10, 2025. The City also posts SB9 application forms on its Planning Guides and Materials page. We use the current code when we evaluate a Thousand Oaks lot.

    How SB9 lot splits work in Thousand Oaks

    Under § 9-4.3704, the City ministerially processes an urban lot split or a two-unit housing development if the lot is in a single-family residential zone. The City defines that, for this article, as a zone where the only residential use allowed as a primary use is a single-residential dwelling on a lot. The project also has to clear the statute's anti-displacement rules and must not be on restricted land, including a historic resource or district, prime farmland, wetlands, or a very high fire hazard severity zone, unless the state's listed exceptions apply.

    A complete application must be approved or denied within 60 days and is deemed approved if the City does not act in that time. If it is denied, the City must return written comments describing the deficiencies and how they can be remedied. The Community Development Director's decision on the parcel map is final and is not subject to appeal. In our partnership you keep your house on one parcel. We design, permit, fund and build a new home or duplex on the second parcel, sell it, and pay your share at the sale.

    Thousand Oaks rules we plan around

    • The split and the new-home plans are filed together. The City generally will not accept an urban lot split application unless a residential development application is submitted at the same time for the newly created parcel (if the property already has a residence) or for both parcels (if the property is vacant), unless a two-unit housing development has already been approved on the property. A building permit for a two-unit project is not issued until the tentative parcel map records, with a narrow exception set out in the code.
    • 1,200 sq ft, 40 percent, and two units. Each new lot must be at least 1,200 sq ft, and neither may be smaller than 40 percent of the original lot. A maximum of two units is allowed on each lot created under this section, inclusive of ADUs and JADUs. New lot lines must be straight and of regular geometry unless existing improvements or the natural environment conflict with that.
    • Owner occupancy. An owner must occupy one lot as their primary residence for a minimum of three years from the date of approval of the final map. The code also says a dwelling unit must exist on the property at the time of approval.
    • A biological resources statement at submittal. The City requires a written statement, prepared by a qualified biologist, landscape architect or other resource expert, affirming that there is no habitat for listed protected species in the vicinity of the property. If such habitat is found on site, the property is not eligible.
    • Access, parking, utilities and hillsides. No new access from an arterial street is permitted in connection with a dwelling unit created under this article. The City generally requires one enclosed parking space, 9 by 20 feet, per primary dwelling unit, unless that would preclude units of 800 sq ft. New utility distribution facilities serving a two-unit project must be installed underground. Hillside and protected-ridgeline standards in the code can also apply, and grading on a natural slope greater than 25 percent is restricted.
    • Approvals expire. An approved urban lot split that is not recorded within three years expires, unless the director approves an extension. A maximum of two 24-month extensions may be approved.
    • City forms. The City publishes the SB9 two-unit and urban lot-split applications on its Planning Guides and Materials page. We use the current forms when we apply.

    Which Thousand Oaks lots qualify for our partnership

    The Municipal Code sets legal eligibility. Our partnership is stricter. We look for owner-occupied, generally flat lots, generally 10,000+ sq ft, with a home generally worth $1,000,000 or more, and a realistic way to give the new parcel street access that does not rely on a new arterial curb cut. Usable, level yard and access matter more than a large total lot size that is hillside, ridgeline or otherwise constrained. If you live in a nearby unincorporated community such as Oak Park, County of Ventura rules apply instead of this article; see our Ventura County guide.

    A realistic timeline

    We plan for about 12 months from start to payout. Because Thousand Oaks generally requires the new-home application to be filed with the lot split, design work has to start earlier than in cities that will process a map alone. The 60-day clock covers a complete application decision, not construction or sale. Sometimes timelines go past 12 months due to unforeseen delays with city approval and construction.

    Local project example

    We share only completed, verified projects. When we finish a Thousand Oaks partnership, its lot size, permit number and results will be listed here.

    Next step

    Read the Ventura County SB9 guide, the eligibility checklist, and schedule a free consultation. We'll confirm whether your lot is in a qualifying single-family zone and whether a partnership is realistic.

    Frequently asked questions

    Must new-home plans be filed with the lot split?

    Generally, yes. Thousand Oaks normally requires a residential development application for the new parcel, or both vacant parcels, at the same time unless a two-unit housing development has already been approved. The code contains specific exceptions.

    What biological-resource statement is required?

    A qualified biologist, landscape architect or other resource expert must provide a written statement affirming no habitat for listed protected species near the property. If such habitat is found on site, the property is not eligible.

    Do nearby unincorporated communities follow this article?

    No. An unincorporated community such as Oak Park follows County of Ventura rules instead. The Thousand Oaks guide applies to parcels under the City’s jurisdiction.

    Find Out What Your Thousand Oaks Land Is Worth

    We cover 100% of the design, permitting, and construction costs. Homeowners typically net $150,000+ and never have to move. Homes generally need to be worth $1,000,000 minimum.

    Final terms are set in a written partnership agreement. See Terms.

    More SB9 Guides in Ventura County