How SB9 lot splits work in La Jolla
The City processes an urban lot split as a Process One (ministerial) Parcel Map. You can apply for the split, the new homes, or both. The City prefers both at the same time, because the order of approvals can change what you're allowed to build later. Under SB 450, a complete application must be decided within 60 days.
In our partnership, your La Jolla home stays on its own parcel. We split off the unused land, design, permit, fund and build a new home or duplex there, sell it, and pay your share at the sale.
City of San Diego rules that matter most in La Jolla
- Coastal Development Permit. IB 409 requires a Coastal Development Permit for every SB9 unit or lot-split application inside the Coastal Overlay Zone. You can check whether your parcel is in the zone with the City's ZAPP map.
- Owner-occupancy affidavit (DS-3062). Before the parcel map records, the record owner signs Form DS-3062 stating they intend to live in one of the homes as their primary residence for at least three years from approval. It's recorded with the County Recorder, and Form DS-3063 is also required.
- No ADUs with a lot split. When a project uses the urban lot split together with SB9 units, IB 409 doesn't allow ADUs or junior ADUs. An existing ADU must be removed or converted into one of the SB9 homes.
- Beach Impact Area parking. Inside the Beach Impact Area of the Parking Overlay Zone, IB 409 requires one off-street parking space per unit unless car-share access within one block is shown.
- Sea-level-rise agreement. For parcels in mapped future sea-level-rise areas of the Coastal Overlay Zone, the owner must sign an agreement with the City about sea-level-rise regulations.
- Eligible zones. RS, RE, RX and RT zones, plus Planned District zones that allow single- but not multiple-dwelling development.
Which La Jolla lots qualify for our partnership
We look for owner-occupied, generally flat lots that are generally 10,000+ sq ft, with a home generally worth $1,000,000 or more. Each new parcel must be at least 1,200 sq ft. Hillside, bluff-top and canyon-edge lots often hit slope, habitat or access limits, so level lots with an unused side or rear yard are the strongest fit.
A realistic timeline
Our plan is about 12 months from start to payout. A Coastal Development Permit is the most common reason a La Jolla project takes longer. Sometimes timelines go past 12 months due to unforeseen delays with city approval and construction.
Local project example
We publish only completed, verified projects. When we finish a La Jolla partnership, its lot size, permit number and results will appear here.
Next step
See the full San Diego County SB9 guide and our 3-year affidavit explainer, or schedule a free consultation.
Frequently asked questions
Does La Jolla have separate city SB9 rules?
No. La Jolla is within the City of San Diego and follows IB 409 and the relevant San Diego Municipal Code sections.
When is a Coastal Development Permit required?
IB 409 requires one for every SB9 unit or lot-split application inside the Coastal Overlay Zone. The City’s ZAPP map can be used to check the parcel.
Can an ADU remain with an SB9 lot split?
When the urban lot split is combined with SB9 units, IB 409 does not permit ADUs or junior ADUs. An existing ADU must be removed or converted into an SB9 home.